JOB
VACANCIES
Olympics organisers are spending millions of
pounds hiring a team of 'equality and inclusion'
managers. Part of their job will be to ensure
that all the construction firms involved with the
2012 Games employ enough ethnic minority and
female builders.
At least ten senior equality executives will be
employed and paid for by the Olympic Delivery
Authority. Five key jobs have already been
advertised with salaries of more than £100,000,
plus bonuses.
The estimated bill for hosting the Games has
already nearly quadrupled from £2.4billion to
£9.3billion and the extra costs will have to be
met from public money, including higher council
tax bills for Londoners. (Source: Daily Mail, Aug/07) |
CAR-FREE
Londons plan to hold the first car-free
Olympics in 2012 is being undermined by the
International Olympic Committees demand for
more than 3,000 chauffeur-driven cars for
dignitaries, officials and corporate sponsors.
These cars will have access to a network of
dedicated lanes, which will be closed to other
traffic for up to two months. Up to 3,000 sets of
traffic lights will also be adjusted to ensure
that the IOCs fleet has fast access to all
venues.
Those whom the IOC insists need cars, in addition
to receiving free access to public transport,
include the 110 IOC members, 400 presidents and
secretary-generals from the Olympic committees of
the 200 competing nations and 450 senior
executives from corporate sponsors.
None of the 10,500 athletes will have access to
the 3,145 cars and will instead travel on a
dedicated fleet of coaches. The eight million
spectators will not be able to travel by car
because the Games venues will have only a small
number of disabled parking spaces. (Source: Times Online, Mar/08) |
|
|
THE OLYMPIC GAMES 2012
Page 1 | 2 | 3
The government failed to account for the
costs of IT when putting together its budget for the 2012
Olympic Games, according to watchdogs of the Public
Accounts Committee (PAC). In its 39th report, the PAC
said the Olympic Delivery Authority had neglected to
include additional costs of £400m, which would cover
"IT and site mobilisation and the costs of the CLM
Consortium", a project management group appointed by
the Olympic Delivery Authority to help it get everything
in on time. This £400m oversight was part of a £900m
increase in the total budget for the Olympic Park,
announced in 2006.
The PAC says the massive underestimate was a result of
using the costs of an "urban development
corporation" as a benchmark for the running costs of
the Olympic Delivery Authority. And they say private
sector isn't leaner than public. The report also found
the authority has "seriously overestimated" the
amount of private sector funding it was likely to
receive. Planners budgeted for £738m of private sector
funding, but it turned out that there was not enough time
to negotiate the necessary contracts, so the money is
unlikely to materialise. The games were originally
expected to cost around £2bn. That figure has since
risen to £9bn. (Source: The Register, Jul/07)
The bill for the 2012 Olympics has
quadrupled to £10billion. International Olympic
Committee officials are so concerned about the impact of
the rise from the original budget of £2.375billion that
they have demanded a full breakdown of costs at a key
meeting with London 2012 chairman Lord Coe. But Lord
Coe's hands will be tied because it is understood the
Government is planning to delay announcing the revised
bill for the Games until July following disputes within
Whitehall on how it is going to be paid. The Government
is also believed to want to settle on a final figure of
just £6billion because of the public relations damage of
admitting the larger figure.
The lower sum does not include the costs of security, VAT
and a contingency fund for overruns that will mean the
cost of the Games will eventually total £10billion. The
main reasons for the rise are:
* More than
£2billion needs to be found to cover the regeneration
costs for east London around the Olympic Park. This was
not included in the original budget.
* At least
£1billion, more than five times that originally though,
will be needed to cover security costs following the
London bombings on 7 July 2005.
* An extra £750
million for infrastructure costs, originally expected to
be met from the private sector, must be included in the
public funding budget because it is not possible to
secure it in time to start building the Olympic Park in
the summer.
* At least
£2.7billion is being demanded as contingency funds to
cover any costs overruns.
Olympics minister Tessa Jowell admitted in November that
an extra £900 million was needed to cover construction
costs inflation and the increasing price of delivering
the project, including a £400 million fee for CLM, the
consortium hired to keep costs in check. Even if most of
the regeneration, security, VAT and contingency costs are
covered by the Exchequer, there is still a shortfall of
£1.6billion, which has to be found from either the
National Lottery or London council tax-payers under the
funding deal agreed between Ms Jowell and Ken
Livingstone.
The £10billion does not include the £2billion required
to run the Games, which is the responsibility of the
London organising committee. Half of this money is
covered by the IOC through sponsorship and the sale of TV
rights. Lord Coe has to raise the other 50% from domestic
sponsorship, merchandising and ticket sales. The IOC is
frustrated by the impact the budget row is having as it
attempts to encourage less-affluent nations such as
Brazil to bid to host the 2016 Games. (Source: Mail on Sunday, Feb/07)
Two of the main venues in the Olympic Park
may have to be nationalised, with the taxpayer paying
nearly £900 million extra as the credit crunch hits the
2012 Games. Ministers will meet Boris Johnson, the Mayor
of London, to consider ways of meeting the soaring bill
after a lack of private investment. Alistair Darling, the
Chancellor, Tessa Jowell, the Olympics Minister, and
Hazel Blears, the Communities Secretary, have yet to
agree how to find the cash, with Ms Blears resisting
pressure to raid at least £250 million from her
department.
Initially the private sector was expected to meet the
full £1 billion cost of the Olympic Village and at least
half the cost of the £400 million media centre. A deal
was supposed to have been reached with Lendlease, the
developer of the Olympic Village, by the end of this
year. But Lendlease has been unable to raise money
because of the current financial crisis and the
athletes accommodation will now be unviable without
extra government funds.
About £550 million of government funding has already
been allocated for Stratford Park and the infrastructure
for the Olympic Village, including electricity cables and
water supply. But an extra £850 million to £900 million
still had to be found for the village through a mixture
of funding from housing associations, private investment
and the taxpayer. So far no money has been guaranteed
from either the private sector or housing associations.
The cost of the village has gone down marginally as the
number of houses was cut from 4,000 to 2,800 as a result
of the housing market slump. The reduction has already
led to fears that accommodation will be cramped, with
athletes sharing rooms. John Armitt, chairman of the
Olympic Delivery Authority (ODA), has argued that further
time should be allowed to reach a deal with private
investors but ministers are under pressure to underwrite
the funding to restore confidence in the Olympic project.
Mr Armitt has said that in the worst-case scenario the
taxpayer might have to foot the whole bill.
An ODA spokesman said: More public sector
investment will clearly be needed for the Olympic
Village, given the problems in the banking sector and the
deterioration in the property market. This would be an
investment in a long-term housing asset that can then be
sold in the future. Commercial discussions are
continuing, and we remain committed to delivering the
overall project within the £9.3 billion budget.
It is understood that ministers will next week discuss an
extra allocation of £450 million for the Olympic Village
and the media centre, although this will not meet the
entire cost of the projects. A spokesman for Ms Blears
said that she expected any extra money to come from the
Olympics contingency fund. Olympic sources said that if
the taxpayer met the full cost of the bill the Government
would have complete ownership of the venues after the
Games and could sell the homes for mixed social and
private housing.
The lack of private investment in the park has already
resulted in scaling down projects and moving venues, and
there is growing concern that this could jeopardise the
parks legacy. Also high on its agenda will be the
fate of the Olympic basketball arena. The arena will cost
£60 million but is only temporary and will thus have no
legacy value. Tessa Jowell, the Olympics Minister, said,
We are not going to lock ourselves into a private
sector deal which will not give best value for the
public. The village will be built, but how much will be
public or private sector will be something that will be
negotiated. If the private sector doesnt put in
equity now, it can do so later. (Source: Times Online, Oct/08)
The taxpayer may have to fund every Olympic
venue because of the credit crunch. John Armitt, chairman
of the Olympic Delivery Authority, said there was an
increased chance that the £900 million Olympic village
may not attract any private funding as planned. During
the 2012 bid, private sector money was pledged for the
media centre and the village while all the sports venues
were to be built from the £9.3 billion publicly funded
budget. Under original funding plans the Government and
developer Lend Lease were to have jointly funded the
village but as credit has dried up the ODA has been
forced to raid £326 million from the Olympic contingency
fund. Mr Armitt confirmed that the ODA could not 'rule
out' a complete failure of private sector funding for the
village. (Source: Daily Mail, Jan/09)
<<< Prev
|
|
|